Question : Project Server 2007 Tasks

Hi, I am the administrator for MS Project Server 2007.  On the PWA home page, I only see "new tasks" that are outdated and complete.   I created a new project plan and assigned myself tasks , published the project to PWA, the project is on PWA but the task do not show up under "My new task".  Does anyone know how I can get the new tasks to show up under "My New tasks" on PWA?

Answer : Project Server 2007 Tasks

I assume you are looking at your tasks in the "MyTasks" area? There are two setting that control what tasks you are seeing:

- in the view options on this page you can select to "Show only current tasks" (or all tasks if NOT checked)
- current tasks are all task from that past that have NOT been completed or NEW tasks that start within the timeperiod from now to the setting in "Server settings".."Task settings and display".."Define current tasks"

Regards

Thomas